The first milestones
1922 | Establishment of first Ferrostaal representation in Lima. |
1938 | Supply and service of 95 MAN Büssing buses for public transport in Lima. |
1956 | Turnkey contract for supply and erection of a blast furnace at the steelworks Siderperu. |
1964 | Turnkey contract for supply and construction of a fertiliser power plant with Uhde, including MAN TURBO syngas compressors and pumps in Cusco. |
1965 | Supply of train carriages by MAN Ferrostaal for the Cusco – Machu Picchu line. |
1969 | Turnkey contract for supply and erection of a blast furnace at the Siderperu steelworks. |
1973 | Supply of 40 MAN Diesel engines for the fishing industry. |
1975 | Supply and training of two type 209 Islay-class submarines. |
1981 – 83 | Supply and training of four type 209 Antofagata-class submarines. |
1982 | First combined cycle gas turbine power plant with heat recovery boiler, La chilina, Arequipa. |
1983 | Turn key contract for a diesel power plant in Tintaya (18 MW) – 4,200 m above sea level. |
1997 | Turnkey contract for a diesel power plant in Mollendo (30MW) for EGA S.A., Arequipa. |